# Not paid on a federal job? How a Miller Act payment bond claim works

Checked November 24, 2026. Plain words, not legal advice. From Benchmate AI: https://benchmateai.com/answers/miller-act-payment-bond-claim

On a federal construction job, your protection if the money doesn't come is the prime contractor's payment bond. A federal law called the Miller Act requires that bond on bigger federal jobs, and it lets people who supplied labor or material and weren't paid sue on it.

The bond only helps if you meet its deadlines. This page covers who can claim, the written notice some contractors have to send, the deadline to sue, and what to keep on file from day one.

## What the payment bond is

Before a federal construction contract over a set size is awarded, the prime contractor has to furnish a payment bond backed by a surety. The law says the bond is for the protection of all persons supplying labor and material for the work.

Under the FAR, the federal buying rules, the Miller Act requires performance and payment bonds on any construction contract over $150,000. For contracts over $35,000 up to $150,000, the contracting officer picks two or more payment protections, and a payment bond is one of the choices. Ask the prime early which one your job has.

## Who can make a claim

Anyone who furnished labor or material for the work and hasn't been paid in full within 90 days after their last labor or material can bring a civil action on the payment bond.

If your contract is directly with the prime, that's the path: the 90-day wait, then the one-year deadline below. If your contract is with a subcontractor and not the prime, you have one more step first: a written notice to the prime.

## The 90-day notice for sub-tier contractors

If you were hired by a sub, not the prime, you have to give written notice to the prime contractor within 90 days from the date you did the last of your labor or supplied the last of your material.

The notice has to state, with substantial accuracy, the amount you're claiming and the name of the party you furnished the material to or did the labor for. One way the law allows is a method that gives written, third-party proof of delivery, to the prime at a place it keeps an office or does business, or at its residence. Pick a delivery method that gives you a signed or tracked record you can show later.

**Payment bond notice to the prime (fill in, send with tracked delivery)**

> To: [prime contractor name], [address]
> Re: Notice of claim on payment bond, [project name], contract no. [number], [job location]
> 
> [Your company] furnished [labor / material: short description] for this project under a contract with [subcontractor name]. Our last labor or material was furnished on [date]. We have not been paid. The amount we claim is $[amount].
> 
> This is our written notice under 40 U.S.C. 3133(b)(2).
> 
> [Your name], [company], [phone], [email], [date]

## The deadline to sue

A suit on the bond has to be brought no later than one year after the day you last performed labor or supplied material. It's brought in the name of the United States for your use, in the federal district court for a district where the contract was to be performed, no matter how much is owed.

The law sets the date from your last day, not from when payment talks end. If payment talks drag on, keep the date in view.

## What to do from day one

None of this is hard. It's mostly writing things down while they're fresh.

1. Ask the prime, before you start, whether the job has a payment bond and who the surety is. If you've supplied labor or material and haven't been paid, the law also lets you get a certified copy of the bond and contract by submitting an affidavit saying so.
2. Write down the contract number and the exact job location from your paperwork.
3. Log your last day of labor and the date of your last material delivery. Your deadlines run from your own last day, so keep your own record.
4. If you're working for a sub, put a reminder on your calendar well before 90 days from that last day.
5. Keep copies of your contract, invoices, delivery tickets and every payment ask.
6. Watch what you sign. The law says a waiver of the right to sue on the bond is void unless it's in writing, signed by you, and signed after you've furnished the labor or material.

## State and local public jobs

The Miller Act covers federal jobs. City, county and state public jobs have their own rules, set state by state. Check your state's law for those, and don't assume the federal deadlines carry over.

This is general information, not legal advice. For a big bill or a payment fight, talk to a construction attorney in your state.

## Questions shops ask

**What is a Miller Act claim?**

It's a claim against the prime contractor's payment bond on a federal construction job. People who supplied labor or material and weren't paid in full within 90 days after their last work can sue on the bond, within the deadlines in the law.

**Do I have to send a notice before I can claim?**

If you were hired by a subcontractor, yes: written notice to the prime within 90 days from your last labor or material, stating the amount and who you did the work for. The notice step in the law is written for people with no contract with the prime.

**How long do I have to file a Miller Act suit?**

No later than one year after the day you last performed labor or supplied material on the job.

**Does every federal job have a payment bond?**

Not every one. Under the FAR, construction contracts over $150,000 need performance and payment bonds. For contracts over $35,000 up to $150,000, the contracting officer picks two or more payment protections, and a payment bond is one option. Ask the prime which your job has.

**What about state or city public jobs?**

Those follow your state's rules, not the Miller Act. Look up your state's law for public jobs, or ask a construction attorney in your state.

## Read next

- [Pay-if-paid vs pay-when-paid: what's the difference?](https://benchmateai.com/answers/pay-if-paid-vs-pay-when-paid)
- [Getting paid as a subcontractor: pay apps, lien waivers and slow GCs](https://benchmateai.com/free/get-paid/subcontractors)

## Next step

Working under a GC on any job? The free Getting paid as a sub guide covers pay apps, lien waivers, retainage and what to do when the GC stops paying.

- [Get the free Get paid on every job checklist](https://benchmateai.com/free/get-paid)
- [Read the free guide](https://benchmateai.com/free/get-paid/subcontractors)

## Sources

- 40 U.S.C. 3131(b): before any contract of more than $100,000 is awarded for construction, alteration or repair of a public building or public work of the Federal Government, a payment bond with a surety is required for the protection of all persons supplying labor and material https://www.law.cornell.edu/uscode/text/40/3131
- 40 U.S.C. 3133: (a) certified copy of the bond and contract on affidavit; (b)(1) a person who furnished labor or material and has not been paid in full within 90 days after the last labor or material may bring a civil action on the payment bond; (b)(2) a person with a direct contract with a subcontractor but no contract with the contractor must give written notice to the contractor within 90 days from the last labor or material, stating with substantial accuracy the amount claimed and the name of the party furnished or worked for, served by a means giving written, third-party verification of delivery at a place the contractor maintains an office or conducts business, or its residence; (b)(3) brought in the name of the United States for the use of the person, in the district court for any district where the contract was to be performed, regardless of the amount in controversy; (b)(4) no later than one year after the day the last labor was performed or material supplied; (c) a waiver is void unless in writing, signed, and executed after the person furnished labor or material https://www.law.cornell.edu/uscode/text/40/3133
- FAR 28.102-1: (a) the Miller Act requires performance and payment bonds for any construction contract exceeding $150,000; (b)(1) for construction contracts greater than $35,000 but not greater than $150,000 the contracting officer selects two or more payment protections, including a payment bond https://www.acquisition.gov/far/28.102-1