Checked November 19, 2026. Plain words, not legal advice.

Both clauses tie your payment to the general contractor getting paid by the owner. The difference is what happens when the owner doesn't pay. Pay-when-paid is about timing: the GC pays you within a set time after they get paid. Pay-if-paid is about risk: the owner paying the GC is a condition of you getting paid at all.

A few words in the subcontract decide which one you signed. This page covers how to tell them apart, what to ask for before you sign, and what to do when the money is stuck.

Pay-when-paid: a clock, not a condition

A pay-when-paid clause says the GC pays you within a set number of days after the GC receives payment for your work. The owner's payment starts the clock.

The question it leaves open is what happens if the owner never pays, or pays very late. Whether the GC still owes you after a reasonable wait depends on your contract's exact wording and your state's law. That's why it matters to read it before you sign.

Pay-if-paid: the owner's risk becomes yours

A pay-if-paid clause makes the owner's payment to the GC a condition of the GC paying you. If the owner never pays, the clause is written so the GC never owes you for that work.

That moves the risk of an owner who can't or won't pay from the GC to you, even though you have no contract with the owner and no say over who they are. How these clauses are treated can differ by state. Don't guess how your state handles it on a big job.

How to spot which one you have

Find the payment section of the subcontract and read it slowly. Look for these signs.

  1. Words like "condition precedent", "only if" or "subcontractor assumes the risk of nonpayment by the owner" point to pay-if-paid.
  2. Words like "within [number] days after the contractor receives payment" with nothing about risk or conditions point to pay-when-paid.
  3. Check whether there's an outside limit: a date or number of days after which the GC pays you whether or not the owner has.
  4. Check what the GC has to tell you if they're holding your money, and when.
  5. If you can't tell which one it is, treat it as pay-if-paid until someone who knows your state's law tells you otherwise.

What the rules say: federal jobs as one example

Private jobs come down to your contract and your state. Federal construction jobs are one example you can read for yourself.

The federal prompt payment clause for construction contracts tells the prime contractor to put a payment clause in each subcontract. That clause obligates the prime to pay the sub for satisfactory performance no later than 7 days after the prime receives payment, out of the amounts paid to the prime under the contract. The subcontract also has to include an interest penalty for payments not made on time.

The same clause covers a prime holding back part or all of a sub's payment where the subcontract allows it. The prime has to give the sub a written notice before the payment is due. That notice has to say how much is being held, the specific causes, and what the sub has to do to fix it, with a copy to the contracting officer. A payment dispute between the prime and the sub is not one the government is a party to.

This is general information, not legal advice. For a big bill or a payment fight, talk to a construction attorney in your state.

What to ask for before you sign

The time to ask is before you sign. None of these is owed to you. They're plain, reasonable asks.

  1. Change "if" to "when": you get paid within a set number of days after the GC is paid, with no condition.
  2. An outside date: the GC pays you within a set number of days of your pay app, even if the owner is late.
  3. A carve-out for problems you didn't cause: if the owner holds money over another trade's work, yours still gets paid.
  4. Written notice from the GC if your money is being held, with the amount and the reason.
  5. The GC tells you when the owner has paid for your work.

When the money is stuck

If the GC says they haven't been paid, keep it about facts and dates. Ask in writing, keep copies, and keep your own deadlines in view while you wait.

  1. Ask the GC, in writing, whether the owner has paid for the period your pay app covers, and when they expect it.
  2. If they're holding your money for a problem with your work, ask for the amount and the reason in writing so you can fix it.
  3. Keep sending your pay apps on time, with the paperwork the subcontract asks for. Don't give them a reason to say your billing wasn't complete.
  4. Keep an eye on your state's lien or payment bond deadlines. Don't let waiting on the GC run you past them.
  5. Sign conditional waivers only, for money you haven't received.
Asking where the payment is
Hi [name], following up on pay app #[number] for [job], $[amount], for work through [date]. Can you confirm whether the owner has paid for that period, and the date we should expect our payment? If any part of it is being held, please tell me the amount and the reason in writing so we can sort it out quickly. Thanks, [your name], [company]

Questions shops ask

What's the difference between pay-if-paid and pay-when-paid?
Pay-when-paid is about timing: the GC pays you within a set time after they get paid. Pay-if-paid makes the owner paying the GC a condition of you getting paid at all, so if the owner never pays, the clause is written so you aren't owed. How each is treated depends on your contract's wording and your state.
Are pay-if-paid clauses legal?
It depends on your state, and we won't guess at yours. Look up your state's law or ask a construction attorney before you sign a big subcontract with one.
How long does a GC have to pay a subcontractor?
Start with your subcontract, then your state's rules. On federal construction jobs, for example, the subcontract has to obligate the prime contractor to pay the sub for satisfactory performance within 7 days after the prime receives payment, with an interest penalty if it's late.
Can I still file a lien if I have a pay-if-paid clause?
Your lien rights and deadlines come from your state's lien law, and whether a pay-if-paid clause affects a lien claim depends on your state. Keep your notices on time either way, and ask a construction attorney if the amount is big.
How do I get a pay-if-paid clause changed?
Ask before you sign. The plainest ask is to change "if" to "when" and add an outside date: you get paid within a set number of days of your pay app, even if the owner is late.

Read next

Sources

  • Federal construction contracts (FAR 52.232-27, Prompt Payment for Construction Contracts): (c)(1) each subcontract must include a payment clause that obligates the Contractor to pay the subcontractor for satisfactory performance not later than 7 days from receipt of payment out of such amounts as are paid to the Contractor under the contract; (c)(2) an interest penalty clause for each payment not made in accordance with the payment clause; (d) and (g) withholding from a subcontractor without a late payment penalty requires a written notice, with a copy to the Contracting Officer, specifying the amount withheld, the specific causes under the subcontract and the remedial actions the subcontractor must take; (i) a dispute between the Contractor and subcontractor on payment does not constitute a dispute to which the Government is a party https://www.acquisition.gov/far/52.232-27