The last resort: notice of intent to lien.

When the reminders don't work, a lien is the step that usually gets a bill paid. Here's what each notice is, the order they go in, a letter template, and your state's official lien law.

Read this first

Lien rules are different in every state, and a missed deadline or wrong wording can cost you your lien rights. This page is general information, not legal advice. Check your state's law below, and for a big bill, talk to a construction attorney in your state before you send or file anything. Only send a notice of intent if you really have lien rights and mean to use them.

The order of steps

  1. Preliminary notice: at the start of the job

    Many states only let you file a lien later if you sent a notice near the start of the job, often within a set number of days of starting work or delivering materials. Who has to send one (prime contractor, sub, supplier) and on what jobs is different in every state. Miss it and the later steps may not be open to you, so check this before the job starts, not after the bill is late.

  2. Your reminders: friendly to firm

    Most bills get paid here. Use the four reminders from the checklist: day 1, day 7, day 14 (then call), day 30 final notice.

    The reminder wording
  3. Notice of intent to lien: the last warning

    A formal letter saying you'll file a lien on the property if the bill isn't paid by a date. Some states require one before you can file; in others it's optional, but it still works because it's serious. Send it well before your filing deadline, the way your state says to send it (often certified mail).

  4. Filing the lien

    A mechanic's lien is a claim against the property for the unpaid work or materials. It's filed with the county, usually the county recorder. Every state sets a deadline, counted from your last day of work or the job's completion, and missing it ends your lien rights.

  5. Enforcing or releasing it

    A lien doesn't last forever. If you aren't paid, most states give you a set time to file suit to enforce it, or it expires. When you are paid, release it promptly; many states require that too.

Notice of intent to lien: letter template

Fill in the brackets. Some states have their own required form or wording; if yours does, use that instead.

[Your company name]
[Address] · [Phone] · [License number, if your state requires it on notices]

[Date]
Sent by: [certified mail, return receipt requested, or the method your state requires]

To: [Owner name(s)]
[Owner mailing address]
Copy to: [general contractor and/or lender, only if your state requires it]

Re: Notice of intent to file a mechanic's lien
Property: [property address and, if required, legal description]

[Company name] furnished [labor and/or materials] for [short description of the work] at the property above from [first date] to [last date].

$[amount] remains unpaid on invoice #[number] dated [date], despite our reminders on [dates].

If we don't receive payment in full, or a signed payment agreement, by [date: check your state's minimum notice period], we intend to file a mechanic's lien against the property as allowed by [your state's lien law citation]. A lien can affect your ability to sell or refinance the property until it is released.

We'd much rather settle this directly. You can pay at [payment link] or call me at [phone] to set up a plan.

[Name], [Title]
[Company name]

Your state's lien law

Links go to each state's own official source. Look for the preliminary notice, notice of intent and filing deadline sections. States without a link: search your state legislature's website for the citation shown.

Back to the Get paid on every job checklist.