How to write a change order

Checked November 11, 2026. Plain words, not legal advice.

A change order is a short written add-on to the job you already agreed to. It says what's changing, what it costs, the new total and what it does to the finish date, and the customer approves it before you do the work. It can be one page or one text.

Most fights over the final bill start with a change nobody wrote down. "While you're here, can you also" turns into "I never agreed to that" a month later. The fix is a habit, not a lawyer: no change without a price and a written yes.

What goes on it

Keep it short enough that the customer reads the whole thing. Six lines cover it.

  1. The job and the date: customer name, address, and which contract or estimate this changes.
  2. What's changing, in plain words. Say what's added, what's removed, and what materials it uses.
  3. The price of the change: one number, or your hourly rate plus materials if you can't know yet.
  4. The new contract total, so nobody has to do the math.
  5. What it does to the schedule: extra days, or "no change to the finish date".
  6. When it's paid: with the next stage, or on the final bill.

Write it before you do the work

The order matters: price first, yes second, work third. Once the work is done, you've lost your leverage and the customer has lost the choice. Stopping for ten minutes to write it up is fair to both of you.

Your state may require this, not only suggest it. California, for example: the Contractors State License Board says a home improvement contract and any changes to it must be in writing, and that a change must be done with a written change order signed by the customer and the contractor before the change is made. Search your state's contractor licensing board site for "change order" to see what applies to you.

If your contract says how changes get approved, follow it. A contract that calls for a signed change order may not be satisfied by a text.

The form to copy

Paste this into a document or your estimate software. Change the brackets to fit the job and your state's rules.

Change order
Change order #[number]
Date: [date]
Customer: [name]
Job address: [address]
Changes the contract dated: [date]

What's changing:
[Plain description of the added or removed work and materials]

Price of this change: $[amount]
Contract total before: $[amount]
New contract total: $[amount]

Schedule: [adds __ days / no change to the finish date]
Payment: [due with the next stage / due with the final payment]

Everything else in the contract stays the same.

Customer signature: ____________  Date: ______
Contractor signature: ____________  Date: ______

The text version for small changes

For a small add on a job where your contract and your state allow approval by text, a text can do the same job. Put the price and the new total in it, wait for the reply, and screenshot it into the job file.

If the customer asks for the change out loud on site, send the text anyway, right then, while you're standing there. It isn't rude. It's how they know the price before they're billed for it.

Change order text
Hi [Name], you asked us to add [what]. That's $[price], which brings the total to $[new total] and [adds __ days / doesn't change the finish date]. Reply YES and we'll do it. No reply, no change.

When you find a problem behind the wall

Some changes aren't the customer's idea: rot under the tub, a bad subfloor, wiring that has to be fixed before you can close up. Stop, take photos, and show the customer before you touch it.

Then write it up the same way. If you can't know the full cost until you're into it, say so: give your rate, the materials you expect, and a not-to-exceed number, and promise to stop and check in if it will go past that.

This is general information, not legal advice. For a big job or a dispute over a change, talk to a construction attorney in your state.

Found-a-problem text
Hi [Name], we opened up [area] and found [problem]. Photos attached. It has to be fixed before we can go on. The fix is [what], billed at $[rate] an hour plus materials, not more than $[cap] without checking with you first. Reply YES to approve, or call me at [phone] and I'll walk you through it.

Bill it so it doesn't get lost

Number your change orders and list each one on its own line of the invoice, with its number and price. A final bill that's higher than the estimate with no lines explaining why is the one that gets argued.

Keep the signed form or the screenshot with the job's photos. If the change is big, ask for payment with the next stage instead of carrying it to the end.

Questions shops ask

Does a change order have to be in writing?
Write it down every time, whatever your state says, because a written yes ends the argument before it starts. Some states require it for home improvement work: California's licensing board, for example, says changes must be in writing and signed by the customer and the contractor before the change is made. Check your own state's licensing board.
Is a text message enough for a change order?
It depends on your contract and your state. A text with the price, the new total and a clear YES is far better than a handshake, and it's a fair fit for small changes. If your contract or your state calls for a signed change order, get the signature.
What if the customer won't approve the change?
Then you don't do it, and you finish the job as it was agreed. If the change is one you can't skip, like a safety problem you found, explain that with photos and stop that part of the work until you've agreed on a price in writing.
Should I charge for small changes?
That's your call, but write them down either way. A no-charge change order that says "added at no cost" shows the customer what you gave them, and it keeps a free favor from turning into an expected one.