How much deposit should a contractor ask for?

Checked November 10, 2026. Plain words, not legal advice.

Ask for enough to cover what you'd be stuck with if the customer backed out: the special-order materials and the days you hold on your calendar. Then tie every other payment to a stage of the work, so the money never runs far behind what you've done. But check your state's rules first, because a state can cap the deposit on home improvement jobs. California does.

There's no single right percentage. A paint job with stock materials needs less up front than a remodel with custom windows on order. The work is picking a number you can explain, writing it on the estimate, and asking for it the moment they say yes.

Check your state's limit first

Before you pick a number, look up whether your state limits home improvement deposits. Search your state's contractor licensing board site for "down payment" or "deposit". The rules differ from state to state, and they can cover the contract wording too.

California is an example of a state with a hard cap. The Contractors State License Board says the down payment on a home improvement or swimming pool job can't be more than $1,000 or 10 percent of the contract price, whichever is less, with no exception for special-order materials. It also says payments can't get ahead of the value of the work done, apart from that down payment.

Rules like these are written for jobs at a homeowner's house. If you're a sub working for a GC, your money questions are different: pay apps, lien waivers and retainage.

How to size it where there's no cap

Add up what you'd lose if they cancelled the day after signing: materials you can't return, anything custom-ordered, and any restocking fees you'd owe your supplier. That's the floor.

Then think about the calendar. If saying yes means you turn down other work for those weeks, the deposit is what makes the slot real. Say so plainly: the deposit is what puts them on the schedule.

Keep it to a number you'd be comfortable explaining to a fair-minded neighbor. A deposit that looks like most of the job up front makes careful customers nervous, and where a state caps deposits it isn't allowed.

Tie the rest to the work

After the deposit, bill by stage, not by date. Pick stages anyone can see: materials on site, demo done, rough-in passed, final walkthrough. Send each bill the day that stage is done.

This keeps you from carrying the whole job on your own money, and it keeps the customer from paying for work they can't see yet. On a big job, more small stages beat a few big ones.

  1. Deposit when they sign: covers special orders and holds the dates.
  2. A progress payment at each visible stage, billed that day.
  3. The final payment the day you finish and walk the job with them, not net 30.

The words for the estimate

Put the deposit, the stages and how changes work on the estimate itself, so nobody is surprised later. Change the brackets to fit your job and your state's rules.

Payment terms, for the estimate
Payment schedule
Deposit: $[amount], due when you sign. This orders your [materials] and holds your start date of [date].
[Stage 1, e.g. rough-in passed]: $[amount], due that day.
[Stage 2, e.g. drywall hung]: $[amount], due that day.
Final: $[amount], due the day we finish and walk the job with you.

Changes: any change gets a written price first. We do the work after you approve it in writing, even by text.

You can pay by [check / card / bank transfer / pay link].

Ask for it while they're saying yes

The best time to collect the deposit is the moment they agree, not three days later in an email. Have a pay link ready they can use from their phone right then.

This is general information, not legal advice. For a big job or a dispute, talk to a construction attorney in your state.

Say or text it
Great, let's get you on the schedule. We take a deposit of $[amount] today; it covers your [materials] and holds [start date]. The rest is billed as each stage is done. Here's the link to pay from your phone: [link]

Questions shops ask

Is there a standard deposit percentage for contractors?
Not one that fits every job or every state. Size it to the materials and schedule you're committing, and check your state's licensing board first, since a state can set a legal limit for home improvement work, as California does.
Can I take a bigger deposit for special-order materials?
Where there's no cap, you can, and it's a fair ask: custom items can't be returned. Where there is a cap, it may not allow it: California's licensing board says its limit has no exception for special-order materials. There, check your state's rules on billing for materials once they're delivered.
What if the customer won't pay a deposit?
Explain what it covers in one sentence: it orders their materials and holds their dates. If they still won't, you can start with a small first stage, or pass on the job. A customer who won't pay anything up front may be showing you how the final bill will go.
Can the customer cancel after paying a deposit?
It depends on your state. In California, for example, the licensing board describes a three-day right to cancel for most home improvement contracts not signed at the contractor's place of business. Check your state's rules and put the cancel terms in the contract.